PeriodEmploying OrganizationCountryProject assignment summery
August 2021 to PresentClient: Engineering and Planning

Consultants/ Soil and Foundation
Limited
Hydro Morphology for 41 Bridges

Funding Agency: Local Government
Engineering Department
BangladeshProject: Hydrological and Morphological Study

of 41 Bridges over Different River
Responsible for establishing morphological
characteristics of rivers, identification of erosion
vulnerable area, river training considering
environmental safeguard in Hydrological and
Morphological Study of 41 Bridges over Different
River
August 2021 to PresentClient: JDI , New Vision Japan
Sirajganj Economic Zone

Funding Agency: Sirajganj Economic

Zone Limited
BangladeshConsultancy service for the model, design, BOQ
for water network, sewer, drainage, water and
waste water treatment

Design of drainage , sewer , water network.
Modeling of local flooding and drainage design.
Model and design of water and waste water
treatment. Provide detail drawings and BOQ of the
infrastructure
August 2021 to Present Client: Bangladesh Army 14th Brigade/
Cave Property Management
Comilla University


Funding Agency: Government of
Bangladesh
Bangladesh Consultancy service for the model, design, BOQ
for water network, sewer, drainage, water and
waste water treatment

Design of drainage , sewer , water network.
Modeling of local flooding and drainage design.
Model and design of water and waste water
treatment. Provide detail drawings and BOQ of the
infrastructure
May 2021-PresentClient: IIFC , Bangladesh Bridge

Authority

Funding Agency: PPP, Korea
Anis Munsi
SPMC
Bangladesh Consultancy service for the transaction and

review of the the Feasibility of Meghna Bridge
PPP
Hydraulic Morphological modeling and hydraulic
design of the bridge, Detailed Hydraulic Report
preparation.
Review the design of the River Training Works
January 2021-May
2021
Employer: 14th Brigade Bangladesh
Army,
Funding Agency: Bangladesh Army
BangladeshHydro Morphology study of two canals in
Jalshiri Abashan
Hydro Morphologic modeling and hydraulic design
of the canals, Detailed Hydraulic Report preparation
January 2021-May
2021
Employer: Delight Engineers Limited,

Funding Agency: Roads and Highway
Department, Government of Bangladesh
Bangladesh Hydro Morphology study of 890 m span bridge
over river Dhalwesari on proposed Dhaka
Middle Ring Road

Hydro Morphologic modeling and hydraulic design
of the bridge, Detailed Hydraulic Report preparation
December 2019-

May 2021
Employer: Heptatech,


Funding Agency: Narayanganj City
Corporation, Government of Bangladesh
BangladeshFeasibility Study for 500MLD Surface Water

Treatment Plant of Narayanganj City
Corporation, 2000 Million BDT

ensure the overall delivery of the project through
examination of the background, objectives and
contents of the project a Long Term Development
Plan shall be proposed. And through justification of
the possibility of the GoB fund and its effectiveness,
technical and economic feasibility a Feasibility
Study shall be conducted,
January 2019-July

2020
Client: Heptatech,

Funding Agency: Narayanganj City
Corporation, Government of Bangladesh
BangladeshFeasibility Study for 100 MLD Waste Water

Treatment Plant of Narayanganj City
Corporation, 1000 Million BDT

ensure the overall delivery of the project through
examination of the background, objectives and
contents of the project a Long Term Development
Plan shall be proposed. And through justification of
the possibility of the GoB fund and its effectiveness,
technical and economic feasibility a Feasibility
Study shall be conducted,
December 2019-
January 2020
Employer: SPMC, Bangladesh
Funding Agency: World Bank, India
Inland Water Transport Authority
BangladeshConsultancy service for implementation Jal
Marg Vikas Project (JMVP) for capacity
augmentation of navigation on National
Waterway-1 (NW-1) , 5369 Crore Rupees
Review the dredging plan
Review the environmental management plan and
healthy and safety
July 2019
To Present
Employer: DDC
Detail Design of Kewatkhali Bridge,
Mymensingh
Funding Agency: Asian Infrastructure
Investment Bank
Mahbubur Rahman
BangladeshConsultancy Services for Feasibility Study and
Detailed Design for Construction
of Kewatkhali Bridge over the river
Brahmaputra at Mymensingh with Railway
Overpass and 4-Lane Approach (including
Service Road) Road
Hydrologic modeling and hydraulic design of the
bridge, Detailed Hydraulic Report preparation
July 2019
To December
2019
Employer: HDD China
Detail Design of 360 m span bridge over
Balu River on Madani Avenue connecting to
Jalshiri Abashan
Funding Agency: Roads and Highways
Department
BangladeshConsultancy Services for Hydro Morphology
Feasibility Study of Balu River Bridge

Hydrologic modeling and hydraulic design of the
bridge, Detailed Hydraulic Report preparation
August 2019
To December
2019
Employer: Asian Development
Bank/DPHE
Detail Design of Shalbagan Reservoir at
Ukhia
BangladeshProject:
TA 9546 BAN: Implementing the Emergency
Assistance
Project under Contract No. 151422-S26118
Hydraulic Modeling of Water Reservoir and detailed
design
January 2019
To February 2020
Employer: Dhaka WASA
North Water Supply Improvement Project,
Funding Agency: Asian Development
Bank, Project Value: 6500 Million BDT,
Project Nature: Design Build
BangladeshProject: Dhaka North Water Supply
Improvement Project, Funding Agency: Asian
Development Bank, Project Value: 6500 Million
BDT, Project Nature: Design Build
Hydraulic Modeling of Piped Water Network.
Commissioning of the network model
August 2018
To
June 2019
Client Cardino/Local Government
Engineering Department
Funding Agency
DFID
BangladeshLGED Pavement and Drainage Manual
Development of the hydrology manual for providing
guidance to LGED Engineers
March 2018
To
July 2018
Employer: Designscape Limited
Connecting Railway Project, Funding
Agency: Bangladesh Rialway, GOB, Project
Value: 8000 Million BDT
BangladeshProject: Mirasarai EZ Connecting Railway
Project

Design of vertical and horizontal alignment of 17 km
of Railway track connecting Mirsharai Economic zone
to Dhaka Chittagong Railway. Compute details of the
earthwork and 3D modeling. Provide BOQ for the
project
August 2018

To
December 2018
Employer: Infrastructure Investment

Facilitation Company
New Railway Project, Funding Agency:
GOB and Government of China, Project
Value: 30000 Million BDT
BangladeshProject: Jamalpur Joydevpur New Railway

Project, Funding Agency: GOB and Government
of China, Project Value: 30000 Million BDT
Hydrologic modelling and determination of flow at
crossing. Determination of Standard High Water
Level at the crossings Compute Scour
March 2018

To
July 2018
Employer: Infrastructure Investment

Facilitation Company
Connecting Railway Project, Funding
Agency: GOB, Project Value: 8000 Million
BDT
BangladeshProject: Mirasarai EZ Connecting Railway

Project, Funding Agency: GOB, Project Value:
8000 Million BDT
Hydrologic modelling and determination of flow at
crossing. Determination of Standard High Water
Level at the crossings. Compute Scour
September 2017

To
February 2018
Employer: Engineering and Planning

Consultants Ltd
BangladeshProject: Hydrological and Morphological Study of

14 Bridges over Different River at Kishoreganj,
Mymensingh, Jamalpur, Rajbari, Kushtia,
Narayanganj, Tangail, and Gazipur Districts
(Package No. CIB-S-58 and CIB-S-60) under
LGED.
Responsible forestablishing
characteristics of rivers, identification of erosion
vulnerable area, river training considering
environmental safeguard in Hydrological and
Morphological Study of 14 Bridges over Different
River at Kishoreganj, Mymensingh, Jamalpur,
Rajbari, Kushtia, Narayanganj, Tangail, and Gazipur
Districts (Package No. CIB-S-58 and CIB-S-60)
under LGED.
June 2017

To
July 2017
Employer: Bangladesh Water Development

Board

BangladeshProject: Climate Smart Agricultural Water

Development Project
Review current relevant policies, legislations, and
procedures/practices of the Government of
Bangladesh (GoB) for land acquisition and population
displacement related infrastructure development and
explain its implication to the proposed project;
Review the National Water Policy 1999 and the
Guidelines Participatory Water Management 2000
and the procedures of registration of the WMOs with
the Chief Water Management within BWDB for
formation of WMOs, their registration and functioning
in the PSM system.
May 2017
To
July 2017
Employer: AI Associates LtdBangladeshProject: Rangamati Tourism Development
Project:
Responsible for preparing Environmental Impact

Assessment and Environmental Management Plans

for various flood control projects. Responsible for

reviewing Environmental Assessment and

Environmental Management Plans for various
Development projects. Responsible for reviewing

Strategic Environmental Planning for municipalities